Daily status report on energy industry recovery efforts in the US Gulf

 

-- The Louisiana Dept of Natural Resources on Oct 7 said operators of onshore and shallow-water wells in a 38-parish region have restored 39,641 b/d, or 19.5%, of the area's daily oil production of roughly 203,139 b/d before hurricanes Katrina and Rita made landfall. The agency added that operators have restored 535,700 Mcf/d of gas production, or 24% of the region's prestorm output of roughly 2.235 Bcf/d.

-- LNG terminal developer Cheniere will begin remobilizing construction activities on its Sabine Pass construction site in west Cameron Parish, Louisiana, Oct 10, and expects activity to return to pre-hurricane levels within the next 5 to 6 weeks. The Sabine Pass LNG receiving terminal will be capable of receiving vessels of up to 250,000 cu meters, and is permitted for 2.6 Bcf/d of sendout capacity in its first phase.

-- The Dept of Energy has received no new requests for loans of crude oil from the Strategic Petroleum Reserve in the wake of Hurricane Rita, a DOE spokesman said Thursday.

-- US gasoline demand has fallen 200,000 b/d, or about 3%, in the past month amid near-record prices at the pump and as two hurricanes wrecked a large part of the Gulf Coast region, the head of the Energy Information Administration said on Oct 6.

-- Chevron has begun start-up procedures at its 325,000 b/d Pascagoula, Mississippi, refinery, and expects the facility could return to normal operations by the end of October. Katrina had damaged the refinery's marine terminal, cooling towers and other equipment, but a perimeter dike spared the facility from flooding.

-- With Sabine Pipe Line on Oct 7 lifting its force majeure at five more interconnects at the Henry Hub in Vermilion Parish, Louisiana, about 145,000 MMBtu in natural gas next-day spot trades were done on the IntercontinentalExchange, an ICE spokesman said. The Henry Hub has not traded spot gas since Rita hit Sep 21 due to flood damage and a power outage. Sabine lifted the force majeure at interconnects with Louisiana Gas System, Texaco Pipe Line/Citgo, the Jefferson Island System and Bridgeline Gas. Sabine's force majeure previously was lifted to Acadian Gas, Jefferson Island Pipeline, Trunkline Gas, Kinder Morgan/Tejas Gas high and low-pressure systems Calcasieu Gas, Natural Gas Pipeline Co of America, Gulf South Pipeline, and Columbia Gulf Transmission. Force majeure conditions continue to be in effect for all remaining points until further notice by Sabine.

-- Louisiana utility Cleco Corp Friday estimated restoration work following Rita will cost the company about $50-mil. Cleco said its liquidity is sufficient to fund restoration costs from Katrina and Rita, which made landfall on the US Gulf Coast Sept 24 and knocked out power to about half of Cleco's 265,000 customers.

-- Entergy Corp early on Oct 7 said 91,000 of its customers in Texas and Louisiana, remain without power after Rita, down from a peak of 766,000. About 75,000 of those still without power are in Texas.

Copyright © 2005 - Platts

Please visit:  www.platts.com

Their coverage of energy matters is extensive!!.