No way found to bury more of power lines in Connecticut

 

By Pam Dawkins, Connecticut Post, Bridgeport -- Dec. 22

The committee charged with finding out if burying more than 24 miles of new high-voltage power lines between Norwalk and Middletown is feasible reported late Monday that it's not.

The Reliability and Operability Committee, made up of electrical engineers from The United Illuminating Co., Connecticut Light & Power Co. and Independent System Operator New England, as well as outside analysts, submitted its findings to the Connecticut Siting Council.

The council will rule in April on phase two of CL&P and UI's plans to upgrade inadequate power transmission lines between Middletown and Norwalk with 345-kilovolt lines capable of handling southwest Connecticut's power demands. Some groups want more than 24 miles of the cables buried, citing reasons including the potential health hazard of overhead lines they worry will generate electro-magnetic fields.

ISO, the region's power grid operator, in June objected to the original plan to bury 24 of the 69 miles of power lines, because it was unsure the buried lines would be reliable, which led to the forming of the ROC.

But the report released Monday included upgrades, such as using a different type of cable and replacing a number of surge arresters to protect against excess voltage at substations, that make burying up to 24 miles of lines -- between the Norwalk substation and the East Devon substation in Milford -- technologically feasible.

"Anything additional would not operate reliably," ISO spokeswoman Ellen Foley said Tuesday of the report's finding.

But Gov. M. Jodi Rell was "deeply disappointed" that the committee didn't offer other alternatives.

In a news release, the governor said, "This report is a long and technical explanation of all the things we cannot do. I had hoped to see more alternatives -- not a laundry list of reasons why other proposals won't work." Rell spokesman Rich Harris said Tuesday the governor wanted suggestions to mediate some residents' concerns about the physical impact above-ground power lines will have on their communities.

But, "We did look at other alternatives," UI spokeswoman Marcia Wellman said Tuesday.

She described the ROC's task as finding ways to maximize the amount of underground transmission lines, and said, "While overhead wire and underground cable do the same thing -- they do so differently -- [underground] cable introduces far more complexity into the system --" At more than 24 miles, underground cable is more likely to fail and deliver power spikes than overhead wires, said Wellman, citing what she called "the physics of electricity." The utilities are now updating their original cost estimate of $600 million to bury 24 miles of transmission lines, Wellman said, to reflect the difference in cable and adjustments to existing substations. The utilities expect to submit those numbers sometime next week, according to Wellman.

The Siting Council, which meets at 10 Franklin Square, New Britain, holds its next public hearing on the lines from 10 a.m. to 5 p.m. on Jan. 5. The council begins hearings on the ROC report on Jan. 11, according to its Web site.

For hearing information, visit www.ct.gov/csc.

 

-----

To see more of the Connecticut Post, or to subscribe to the newspaper, go to http://www.connpost.com .

(c) 2004, Connecticut Post. Distributed by Knight Ridder/Tribune Business News. For information on republishing this content, contact us at (800) 661-2511 (U.S.), (213) 237-4914 (worldwide), fax (213) 237-6515, or e-mail reprints@krtinfo.com. UIL, NU,