State, Feds Battle for Control
Electric reliability has always gotten the
runaround. Today, some state regulators would say
that they are getting the end-around.
It may sound like a repeat but it is a really a
re-make. The Obama administration, of course, has
given a high priority to updating the country’s
transmission system, which would become more
efficient and therefore make room for more green
energy. Earlier laws that have given more permitting
authority to federal regulators have largely
flopped.
So, the president wants to
alleviate congestion by giving dual authority to
both state and federal policymakers. The
administration says that such a tack is “more
efficient” and would result in key wires getting
built. The states disagree, saying that their
authority would be usurped and that the concerns of
local citizens would be ignored in favor of utility
companies.
“To the extent that this proposal is motivated by a
desire to reduce barriers to transmission, it
fails,” writes Charles Gray, executive director of
the
National Association of Regulatory Utility
Commissioners. “It relies on a tortured reading
of the statute that would cause uncertainty,
litigation, damage to State and federal relations,
and delays in transmission development.”
Recall the Great Blackout of 2003 that rolled
through the Northeast and parts of Canada? After
that, the 2005 Energy Policy Act gave the
U.S. Department of Energy the ability to assign
national interest electric corridors in those areas
that have capacity constraints. The Federal Energy
Regulatory Commission (FERC) would then have
backstop permitting authority -- to bypass state
regulators if they have failed to act within a year.
More than six years later, only two projects have
gone to the FERC and asked those regulators to
assert their “rights” under federal law. Those
projects, based in the Southwest and Mid-Atlantic,
have since withdrawn their requests citing both a
decline in the demand for electricity as well as
adverse court rulings.
In one case, the U.S. circuit court of appeals said
that if the states rule within a year against new
lines, then FERC can’t overrule them. In a second,
the judges said that the Energy Department must
consult with the stakeholders before creating
national transmission corridors.
“Unifying federal authority with respect to siting
interstate transmission projects would allow a more
efficient, direct process," writes FERC. "Clearly,
the backstop transmission procedure established by
Congress has not yet been effective.”
Green Growth
The Energy Department says that it will come up
shortly with a new proposal. Beyond having the feds
work alongside the states, the agency may give FERC
its duties and have it draw up the national interest
electric corridors. FERC wants that job and says it
would evaluate each proposal on a case-by-case
basis.
Giving the feds a greater say in transmission has
appeal among both industry and certain
environmentalists.
The National Electrical Manufacturers Association
says that giving FERC the ability to designate
high priority areas as well as allowing it to review
cases alongside the states would reduce congestion.
The
Natural Resources Defense Council generally
agrees, although it wants more green energy to flow
through those new wires. It says that the process
will not short circuit state regulators, noting that
the transmission process would be “transparent and
inclusive.”
The North American Electric Reliability Council adds
that if action is not taken to build out the
national grid, it will harm the growth of renewables
that must be transported from isolated regions to
urban areas. It has said that 11,000 miles of
high-voltage transmission lines must get built in
the very short term.
But the state regulators have enjoined some in the
environmental community to oppose the Energy
Department’s proposal. Many green groups want to
first encourage conservation before considering more
transmission -- lines that some fear would run
roughshod through sensitive habitat.
While the Obama administration says that the
proposed process would go smoother, the public
utility commissions beg to differ. They are saying
that not only would the FERC quell their concerns
but also that the Energy Department and FERC are
supposed to watch each other to prevent too much
federal control.
“If Congress had intended this, they would have
simply given this authority to FERC in the first
place,” writes regulator Gray. “Indeed, it is easy
to imagine developers pursuing a FERC corridor
designation and running the clock on State-siting
processes in an attempt to circumvent State-siting
review.”
The Energy Department has indicated that it will
devise a new plan that allows for more federal
authority in the permitting process. Because the
states will oppose that, more lawsuits will come and
the whole episode will play out all over again.
EnergyBiz Insider has been been nominated in 2010
and 2011 for Best Online Column by Media Industry
News, MIN. Ken Silverstein has also been named one
of the Top Economics Journalists by Wall Street
Economists.
Follow Ken on www.twitter.com/ken_silverstein
energybizinsider@energycentral.com